Installation Ready AC Power
Qualified personnel can follow the steps below to identify issues if the Ready AC Power system is not producing energy.
Status and Error Indicators
Startup LED
One minute after DC power is applied, a short red LED flash indicates that the Microinverter startup sequence was successful. Two or more short red flashes indicate an error during the microinverter setup.
Operating LED
GFDI Error
The red LED flashing 4 times indicates that the master panel has detected a GFDI error in the photovoltaic array. Until the error is resolved, the LED will continue to flash red 4 times.
Never disconnect DC cables while energized. Ensure no DC current flow before disconnecting. An opaque cover can be used to shield the modules before disconnecting them.
DC/AC Conversion Electronics Not Working
Two types of problems can occur:
To quickly verify if the problem is communication or the electronics:
Troubleshooting Non-Working Conversion Electronics
Only connect slave panels provided in the kit to the master panel. Connecting photovoltaic modules other than those in the Ready AC Power kit may cause damage, injury, and void the warranty.
Ready AC Power is an on-grid system, and it is necessary to comply with the local grid connection regulations in the installation country.
Need assistance?
Request SupportInstallation and Startup